victor wrote:Glups! Ok, I understand the restriction but now I have a problem.
Like the move task system is a bit poor I actually use a manual procedure to dont do every task a project and dont overload the jump to list. I use this procedure until trackstudio has a good move task solution.
Well I have defined a subproject category and practically all my projects have subproject category. I only use project category for four main folders.
Only the administrator can move tasks because the procedure is very manual.
The procedure?
- first I change the category for the new parent task and change it to project category.
- I move the task to the new parent (that now appear in the tasks list).
- Finally I come back the new parent category task to subproject.
And now?... what I can do?... could you allow to the administrator change the category of a task?
Thanks
If we allow move task to any task (by #) - does it solve your problem ?